Piling is complete on the Victoria Pass section of the Great Western Highway. All 54 major foundation piles for the new Mitchell's Causeway bridge structure are now drilled into the bedrock. They will carry the reinforced concrete road deck. Final designs for an extra eastbound climbing lane have been released. Over the next six weeks, crews start building a five-metre-high retaining wall for it. When finished, the full 2.7-kilometre climb from Little Hartley to Mount Victoria will have two uphill lanes.
Why it mattersTwo uphill lanes give cars and caravans room to overtake heavy vehicles on the steep climb. Until then, the pass stays off your route while work continues to restore access.
Before your next run
Plan Blue Mountains runs on the basis that Victoria Pass stays shut. Catherine King says work is on track to reopen it to traffic by the middle of 2027. Build your route and timings around that, not the old road.