Company · no NHVR reference: fined $10,000, speed, 15 July 2020
Party
- Party
- Company · no NHVR reference. The NHVR publishes court outcomes without the defendant's name.
- Type
- Company
- Role
- Role not stated
The proceeding
- Decision
- Convicted
- Court
- Forster Local Court (Local or Magistrates)
- Jurisdiction
- New South Wales
- Hearing date
- 15 July 2020
- Law
- Heavy Vehicle National Law
- Provisions
- s 93
- Offence
- Speed
Facts
A Kenworth B-Double combination was directed to stop at the Jones Island Heavy Vehicle Checking Station on 19th February 2020. Tests were carried out and it was found that the speed limiter was set to 125.5 km/h – more than 25 per cent above the allowed threshold. The matter was heard in Forster Local Court on 15 July. The prosecution submitted that the offence was at the higher end of seriousness, as the company’s truck was able to travel at more than 25 per cent above the maximum speed limit, creating a real risk to public safety.
As reported by NHVR.
Penalty
- Fine
- $10,000
What the record would have shown
Speed limiter checks and the vehicle's own speed records, reviewed on a set day, with what was done about each finding. How the record works →
Comparable actions
| Defendant | Offence | Jurisdiction | Decision | Date | Record |
|---|---|---|---|---|---|
| Karl O’Sullivan | Other | NSW | Convicted, fined $7,500 | 1 May 2024 | View the record of Karl O’Sullivan, 1 May 2024 |
| Georgia Campbell | Other | NSW | Convicted, fined $5,000; other order | 19 February 2025 | View the record of Georgia Campbell, 19 February 2025 |
| Capital Lines and Signs Pty Ltd | Primary duty | NSW | Convicted, fined $38,000 | 11 November 2024 | View the record of Capital Lines and Signs Pty Ltd, 11 November 2024 |
| Profect Construction Pty Ltd | Primary duty | NSW | Convicted, fined $45,000 | 4 November 2025 | View the record of Profect Construction Pty Ltd, 4 November 2025 |
| Crawfords Freightlines Pty Ltd | Primary duty | NSW | Convicted, fined $90,000 | 27 August 2021 | View the record of Crawfords Freightlines Pty Ltd, 27 August 2021 |
Sources
- NHVR: Court outcomes (read 14 October 2026)
Something here wrong? Report an error and name the source that shows it.